Plan Materials at Operation Start

This field applies to MRP and APS.

When the system is planning released jobs and production schedule releases, this field controls whether the materials for a job or production schedule release are required to be available at the operation's start date or at the job/PS release start date.

NOTES:

MRP Processing

When MRP generates a PLN to satisfy a demand, it always plans the materials to be due at the start of the job. For jobs and production schedule releases, MRP considers the Plan Materials at Operation Start field when the following conditions are true:

The table below summarizes the other factors that determine how MRP plans the due date of materials:

Plan Materials at Operation Start NOT Selected
Job Scheduled AND Use Scheduled Times in Planning selected? Job Start Date Materials are due at
No Not blank Job's Start date
No Blank Job's End date - Fixed Lead Time + (Variable Lead Time * Qty)
Yes n/a Job's internal projected start date (calculated by the Scheduler--not displayed elsewhere)
Plan Materials at Operation Start Selected
Job Scheduled AND Use Scheduled Times in Planning selected? Operation Start Date Job Start Date Materials are due at
Yes Not blank n/a Operation Start Date
Yes Blank n/a Job's internal projected start date (calculated by the Scheduler--not displayed elsewhere)
No n/a Not blank Job Start Date
No n/a Blank Job's End date - Fixed Lead Time + (Variable Lead Time * Qty)

APS Processing

If the job or production schedule is released but NOT scheduled, APS plans the materials based on the setting of the Plan Materials at Operation Start field.

  1. When APS generates a PLN to satisfy a demand, it always plans the PLN's materials to be due at the start of the operation.
  2. If you then firm the PLN into a job or production schedule and rerun APS Planning, it again plans the materials at the start of the operation.
  3. Finally, when you release the job or production schedule and rerun APS Planning, the Plan Materials at Operation Start parameter determines whether the system plans the materials at the start of the operation or at the start of the job.

NOTES: These notes apply if you are using APS.