Material Planner Workbench Overview

The Material Planner Workbench offers you an alternative method for generating supply orders that satisfy requirements without needing to run MRP or APS. The system considers the demands and supplies at all warehouses across the entire plan horizon and creates planned supply orders to cover all instances where the on-hand inventory is below safety stock. The system places the item replenishment data on the Material Planner Workbench, where you can review it, make changes, and firm it into purchase orders, purchase requisitions, jobs, production schedules, MPS orders, and transfer orders.

Material Planner Workbench Generation form

The Material Planner Workbench Generation form generates planning data that will be used to populate the Material Planner Workbench form. You can generate data from one of the following sources: MRP or APS plan output, item replenishment data (that is, a netting of all demands and supplies at the warehouses), or cross-referenced orders. The system uses the following three methods to generate the planned supply orders:

The following chart shows which fields on the Material Planner Workbench Generation form correspond to each source:

MRP, APS, or MPS Item replenishment data Cross-referenced orders
Use Planned Data Warehouse Order
  Item Project
    Transfer
    Job

NOTE: Configured items are not included in the generation.

Material Planner Workbench form

Once you have run the generation, open the Material Planner Workbench form to view the planned orders.

NOTE: Not all item information is stored in the data file generated by the Material Planner Generation form. When you open the Material Planner Workbench form, some item information is pulled from the Items form. If an item's Configuration Flag field was selected between the time when you generated your data and the time when you opened the Material Planner Workbench form, the orders associated with those items can no longer be firmed and will cause the process to stop. Delete these workbench records to continue firming orders.

When data populates the Material Planner Workbench form, it is divided into six views based on two sets of criteria.

If you're using MRP, APS, and MPS data or item replenishment data, the records are assigned to views according to the following rules:

If you're using mass cross-referencing, the records are assigned to views according to the following rules:

A Summary form allows you to see the domestic currency value of the data currently loaded on the Material Planner Workbench along with the value of only the items that are selected to be processed.


Related Topics

Firming Planned Orders Through the Material Planner Workbench

Generating Data for the Material Planner Workbench