Creating an Engineering Change Notice Line Item

ECN line items define the changes to the inventory item, job order, or estimate job, at an operation, material, or material reference level.

  1. Open the Engineering Change Notice Items form.
  2. Select Actions > New. The ECN must have a status of Requested.
  3. Enter data in the required fields:

    NOTE: Current Operation, Current Materials, or Material References refers to the inventory item's current operations, materials, or material references.

    Line Item Required Fields
    Operations Work Center

    Move

    Queue

    Setup

    Offset

    Backflush

    Mach Hrs per Piece or Pieces per Mach Hr

    Labor Hr per Piece or Pieces per Labor Hr
    Materials Seq

    Type

    Quantity

    U/M

    Probable

    Increm Price

    Ref Type

    Per/Unit or Lot

    Unit of Measure
    Costs Material

    Labor

    Fixed Overhead

    Variable Overhead

    Outside
    References Seq

    Reference Seq

    The ECN Line Items fields are:

  4. Select Actions > Save.


Related Topics

Engineering Change Notice Steps