Create a Revenue Milestone
- Choose the project number on the Revenue
Milestones form. Only projects with a WIP relief method of Revenue
Recognition display in the drop-down.
- Enter the milestone number in the Milestone Number field.
- Enter a description in the (Description) field.
- Enter the planned complete date on the General tab. The planned
complete date is the date you expect to print and post the milestone.
- Enter the planned cost amounts.
- Enter the planned revenue amount.
- Select the milestone cost calculation method on the Revenue Recog
tab. This is a required field:
- Manual - If you choose manual,
you must manually enter the milestone costs on the General tab
of the Revenue Milestones or Estimate Revenue Milestones forms.
- % Of Project Cost - This
method multiplies the total planned cost by the amount in the
Percentage field.
- % Of Milestone Revenue -
This method multiplies the total planned revenue by the amount
in the Percentage field.
- % Of M/S Requirements - This
method multiplies all task costs by the amount in the Percentage
field. The system adds all forecast costs from the % Complete
tab on the Project Tasks form for all task requirements and all
projected costs from the resource requirements on the Project
Resources Cost tab to get all task costs.
- Unrelieved Cost - This method
calculates the cost that has accumulated since the last revenue
recognition milestone posting.
- Custom - The custom option
is reserved code to be used if there are custom processing routines
created for your company.
- Select the milestone revenue calculation method:
- Manual - If you choose manual,
you must enter the revenue amount on the Revenue Milestones or
Estimate Revenue Milestones forms.
- % Over Milestone Cost - The
percentage you enter in the Percentage field serves as the markup
of the milestone cost. This markup is the revenue that is recognized.
- % Of Project Revenue - This
method multiplies the percentage you enter in the Percentage field
by the total planned revenue from the Revenue tab of the Projects
form.
- Custom - The custom option
is used if there are custom processing routines created for your
company.
- Select the Requirements tab to add requirements for each milestone.
It is not necessary to have a requirement for a milestone.
- If you are utilizing advance payments, use the Create
Advance Payment Invoice and Advance
Payment Deduction Amount fields to add advance payment information.
- Save your changes.
Related Topics
Projects Overview