You can send planned orders (forecasts) for purchased items to a vendor electronically using the Outbound 830/DELFOR transaction. The planned order for the purchased item is created using the MRP Planning or APS Planning activity.
If this field is not selected, the system does not generate the EDI planning information or export 830/DELFOR transactions.
The system only creates planning information for the Rank 1 vendor for this item, as defined on the Vendor Contracts form.
Whenever you run APS or MRP planning, these forecasts continue to be created until the options are turned off in the vendor profile.
After the planned orders have been generated by the MRP or APS program, the forecast information is ready to send to the vendor.