Break Rule

This field applies to APS.

The field controls how the system can fit this operation into the available time of the required resources, considering the resources are unavailable for certain periods when they go off-shift or are already planned to work on other demands. Options are:

The setting of this field also affects how the system is able to reallocate resources if an operation is interrupted by a resource going off-shift or working on another demand. See Handling Resource Reallocation During Interruptions for more information.