Setting Up Service Contract Maintenance Schedules

Service Contract Maintenance Schedules Setup

Any contract line that requires routine maintenance must have at least one contract maintenance schedule defined in order for an SRO to be generated at the specified frequency.

Each maintenance record contains the frequency of the visits and a description of the work that needs to be done. Attached to the maintenance record are units that need serviced along with the operations that need to be completed. Other settings include:

Process Flow

Follow these steps to set up a schedule:

  1. Select Actions > New on the Service Contract Maintenance Schedules form.
  2. Specify this information:

    Contract

    Select the unique alphanumeric used to identify a contract.

    Maint Line

    The default order is 1, 2, 3, and so on, but you can specify the value manually when entering additional line records.

    Status

    The status of the contract is displayed. The status can be estimate, template, open, hold, or closed.

    Description

    Specify a description for the contract.

    Start Date

    The current date is displayed. You can specify a different date.

    SRO

    Select the SRO.

    Frequency

    Select a frequency to determine how often to produce maintenance service orders. Options are:

    Date Duration

    Specify the length of time the maintenance will take. This value is used in conjunction with the Increment or Duration Type field to determine the calculation.

    Increment

    Select the increment time for the schedule. Available choices are Day(s), Month(s), Year(s), or Meter.

    Down Time

    Specify the number of days needed to perform maintenance work.

    Lead Time

    Specify the length of time needed to prepare for the work to be performed.

    Lead Time Type

    Select the frequency to use in conjunction with the Lead Time to determine when the maintenance service order is created. Options are:

    Cust PO

    Specify the customer purchase order. A value is required for this field if the PO Required flag is selected.

    Auto Generate PO

    Select this check box to automatically create a purchase order for the maintenance service order generated by SRO creation routine.

    Auto Create Incident

    Select this check box to have one incident created for each SRO generated from the Service Contract SRO Generation Utility.

    Last SRO

    The last service order that was generated for the maintenance line is displayed.

    Lead Partner

    Select the partner responsible for the SRO.

    Schedule Basis

    Select a value to determine whether maintenance service orders are generated based on the end date, close date, or maintenance date of the last SRO.

    Schedule Future

    Select this check box to create maintenance service orders based on the frequency selected, and regardless of any prior SROs open in the system for the selected maintenance line.

    Use Fixed Price

    Select this check box to add a line and a project/fixed operation to the SRO as it is created for billing purposes.

    Fixed Price Billing Amount

    Specify the billing amount to be assigned to the created SRO when the Use Fixed Price check box is enabled.

    Include Tax in Price

    Select this check box to include any tax amounts as part of the price. This option applies for the billing type of project/fixed.

    All Operations From SRO

    Select this check box to create a service order operation for each operation on the selected SRO or SRO template.

    All Lines from Contract

    Select this check box to create a service order line for every line on the contract.

    All Units From Customer

    Select this check box to create a service order line for every unit owned by the customer on the contract.

  3. Save the new record.

Related Topics

About SyteLine Service

Using Contracts to Track Maintenance Agreements for Customers

Using Contracts to Generate Service Orders