Resource Utilization
Use this form to view the load on your resources
for a specified time period and under a specified threshold of utilization.
The Scheduler version of this form does not display any information
until you run the Scheduling activity. The APS version of this
form does not display any information until you run APS Planning.
NOTE: If the
Use
Planning Output for Scheduling planning parameter is selected,
the Scheduler version of this form displays the output from running
APS
Planning instead of the Scheduling activity.
To display the utilization records:
- In the Start Date field, select the starting date for
the period you want to analyze.
- In the Intervals fields, select the method in which
to display the utilization records. For example, enter 7 in the
first Intervals field and select Days from the drop-down list
to display 7 records, each representing a one-day time period.
- In the Threshold field, enter a percentage to filter
the display by the utilization of the resources. The grid displays
records only for resources that have Utilization percentages greater
than or equal to the Threshold.
- If desired, select Exclude Infinite Resources to exclude
all infinite resources from the analysis display. In APS mode,
infinite resources are those resources in which the Infinite Planning
field is selected on the Resources form. In the Scheduler, infinite
resources are those resources in which the Infinite Scheduling
field is selected on the Resources form.
- If desired, you may filter on a specific resource by selecting
the resource in the Resource column in the grid.
- Click the Filter-In-Place button to display the utilization
records.
Each row in the grid corresponds to a resource and time interval
in which the utilization occurs. The rows are sorted by descending
utilization (that is, the most critical bottleneck resources are listed
first).
After identifying a bottleneck resource, you can select a utilization
record and click the Load Profile button to launch the Resource Load
Profile - Scheduler form or the Resource
Load Profile APS form and determine the cause for the over-utilization.
Related Topics
APS Overview
Resources Overview
Scheduling Overview
Analyzing APS Output
Analyzing Scheduler Output
Resource Load Profile - Scheduler
Resource Load Profile APS