Resequencing Scheduled Jobs and Operations
This topic describes how to adjust the sequence of
scheduled jobs and operations for specific resources or for all resources
in a specific resource group.
Displaying Schedule Records
- Run the Scheduling
activity (to adjust the work sequence, you must have run this activity
at least once).
- Open the desired sequencing form:
- In the Resource field or Resource Group field, select
the resource or resource group you want to adjust the schedule for.
- In the Dispatch Interval field, enter the number of hours
into the future to retrieve schedule records. The interval starts
from the start date of the last run of the Scheduling activity.
- Click the Filter-In-Place button to retrieve the schedule records.
- On the Resource Sequencing form, the grid displays all
jobs and operations the resource is scheduled to perform for the
displayed period.
- On the Resource Group Sequencing form, the grid displays
the jobs and operations the resource group is scheduled to perform
(no specific resource is indicated).
- Records are shown in the grid in the order the Scheduler sequenced
them, usually in order by start date.
Changing the Work Sequence
You can fine tune the schedule in two ways: by using the Resource Sequencing
Sort Setup form to define automatic sort priorities, and by manually adjusting
the sequence of records in the grid.
To establish automatic sort default priorities:
- Open the Resource Sequencing Sort
Setup form.
- Specify a resource.
- Create up to six sort criteria by selecting a table, selecting
a field name, entering a field label, and specifying either ascending
sort of descending sort.
- Use the Move Up and Move Down buttons to set the priority of the
sort criteria.
- Save the record.
- Open the Resource Sequencing
form.
- Click Sort to apply the
sort specifications defined on the Resource
Sequencing Sort Setup form.
To manually adjust the records in the grid:
- Choose a schedule record by selecting a row in the grid.
- Click the Move Up or Move Down buttons to move the
record up or down in the list.
- When you are finished changing the sequence, select Actions
> Save.
Related Topics
APS Overview
Resources Overview
Scheduling
Overview
Resource
Group Sequencing
Resource Sequencing