APS Steps
This topic describes three categories of steps associated 
 with APS planning:
Your system administrator or installation consultant might have already 
 performed these initial setup steps. In some cases, these steps must be 
 repeated periodically. For details, see the Infor SyteLine Installation Guide.
	- Use the Planner Manager utility to start the Planner Database Manager 
	 and create at least one planner database. 
 To start the Planner Manager, on the utility server, select Start > Programs > Infor > Planner Manager.
 For instructions to create planner databases, see the Planner Manager 
	 online help or the Infor SyteLine Installation Guide.
- Specify the planning 
	 parameters for your APS system. Perform these steps: 
	
		- Set 
		 up the production alternative (required).
- Enter a site record for the local site (required if you will 
		 be using APS or the Scheduler).
- Enter a site record for each of your supply sites that provide 
		 component parts to this site (required if you will be running 
		 APS 
		 Planning in Global 
		 mode).
- Define options located on the General 
		 and Advanced tabs.
 
- Select the appropriate Operation Scheduling option on the 
	 Shop Floor Control Parameters form. 
	 
	This parameter controls whether job operations are planned and scheduled 
	 by the number of pieces remaining to be completed or by the number 
	 of hours remaining to be performed. 
- If you are not using global planning, to replicate transfer orders 
	 to your supply sites, set up transfer 
	 order replication. If you are using global planning, but some 
	 sites are not participating in global planning runs, set up transfer 
	 order replication for those sites.
Perform these tasks on a regular or periodic basis to maintain your 
 production data for planning.
	- For the users that will perform the Get 
	 ATP/CTP function on transactions such as customer orders, job 
	 orders, forecasts, estimates, and so on, assign their user IDs to 
	 the user 
	 group that provides the appropriate permissions. 
	The APS - Set Due Date < Projected and APS - Override 
	 Projected Date user groups allow the user to override the calculated 
	 availability date and enter an earlier date with which to plan the 
	 demand. For more information, see Availability 
	 Results. 
- Define planning options for your items. 
	 
	Options on the Planning and Additional Planning tabs 
	 of the Items form determine how APS handles each inventory 
	 item. 
- If you want APS to consider more than two decimal places in quantity 
	 values, specify the number of decimal places in the Planning Precision 
	 field for each unit 
	 of measure code you are using.
- Define lead 
	 times for purchased items.
- Set up lead 
	 time shifts to represent business days for purchased items. 
	NOTE: If you 
	 do not do this, lead times assume 24-hour days and seven-day weeks. 
- To define the available working times your resources can process 
	 operations, set up scheduling 
	 shifts. 
	A default shift is predefined. 
- Create work 
	 centers for tracking operation costs.
- Create resource 
	 groups and resources 
	 for performing the operations.
- Create 
	 the current routing/BOM for each of your items. 
	Specify one or more resource groups on each operation in the routing. 
	 When you create a job, you can copy 
	 the current routing/BOM to the job (it serves as a template for 
	 the job routing/BOM). 
- To specify the time periods for organizing the output data on the 
	 Planning Summary Display, Master Planning Display, and 
	 Master Planning Report, create the Planning 
	 Horizon Calendar.
- Enter forecasts 
	 for items.
- Make sure item low-level 
	 codes are correct. To update the low-level codes, run the Current 
	 Bill of Material Processor and Job and PS Bill of Material 
	 Processor.
- To group items that are authorized to be manufactured, create production 
	 schedules. 
	Production schedules are synonymous with work-orderless, or rate-based, 
	 manufacturing. APS views a production schedule as a regular demand 
	 for items with a due date. Thus, a daily production schedule for 10 
	 items per day is planned as 5 daily orders for 10 items. 
- For items that you want to plan separately (usually high-cost items), 
	 create a master 
	 production schedule. 
	As with production schedules, master production schedule orders 
	 are considered demands in APS. 
- Specify order 
	 priorities for planning demands.
- Test the viability of different production situations without affecting 
	 your database.
The life cycle for a single demand usually proceeds through the APS 
 and scheduling functions like this:
	- The order entry user promises the order (demand incrementally planned 
	 during Get ATP/CTP).
- The planning user runs the APS Planning activity. APS generates 
	 planned order to fill unsatisfied demand quantity.
- The planning user firms the planned order into a job (for example, 
	 on the Planning Detail form) 
	 and releases it.
- The scheduling activity schedules the job and generates the dispatch 
	 list.
- The job is executed on the shop floor according to the dispatch 
	 list.
- The order is shipped.
The next two sections describe the routine tasks associated with these 
 events in a demand's life cycle.
Nightly Steps
You can place these tasks on the Background Queue to be run nightly, 
 when few or no users will be saving changes to records that are included 
 in the plan and schedule. For more information, see Scheduling 
 Reports and Utilities to Run in the Background.
	- Run the Scheduling activity 
	 using Days 
	 to Schedule value that equals the Plan 
	 Horizon value for the APS function.
- Run the APS Planning activity. 
	 
	If you are using APS in a multi-site environment, you can use the 
	 Global mode to plan all demands at all sites. Usually you will 
	 run APS with a long horizon such as one or two months. 
Daily Activities
These activities can happen in parallel.
	- Create demands/promise orders during order entry and other daily 
	 activities. When you create a demand in the system, you can use the 
	 Get ATP/CTP function to project completion dates and to insert 
	 the demand into the current plan.
- Analyze 
	 the planning output and determine the causes for any lateness.
- Respond to the exception messages that display on the Exceptions 
	 Report or Planning Detail 
	 form.
- To determine when you must generate and release a job order or 
	 purchase order to ensure that an item is available when needed, use 
	 the Material Planner Workbench 
	 or Order Action Report.
- Firm planned orders using the Planning 
	 Detail form or the Material Planner Workbench form.
- Execute production according to the dispatch list (generated by 
	 the Scheduling activity).
- Record 
	 the status of operations (setup time, move time, and so on) for 
	 costing and scheduling purposes.
Troubleshooting
For descriptions of error messages you may encounter during any the 
 above steps, see Troubleshooting 
 MRP and APS.
 
Related Topics
APS Overview
About Incremental 
 Planning and ATP/CTP
Analyzing 
 APS Output
Configuring 
 a Job or Item
Copying a Job Order
Creating 
 APS Alternatives
Creating a Job 
 Order
Creating 
 a Job Order Manually
Cross-referencing 
 a Job Material to a Job
Defining Lead Time 
 for APS Planning
Defining the 
 Work Week
How 
 APS Replenishes Safety Stock
Issuing 
 Materials to a Job Order
Job Steps
Planning 
 a Job's Operations
Releasing a Job
Running APS 
 Planning
Scheduling a Job Order
Setting 
 Up Planned Transfer Order Replication
Troubleshooting 
 APS
Using Lead Time 
 Shifts
Using 
 Lot Sizes with MRP and APS
Using 
 Supply Usage Tolerance
Writing 
 a Custom Operation Calculation